ERP Milestones

Complete Milestone Date
  Overall Project Started  
   √   Coordinating Committee Convened 02-2006
Project Kickoff – Presentation of Global Project Plan 03-2006
  Data Standards  (General Person) Ongoing
Sunset Viking 08-2008
Sunset SIS Plus 03-2010
√ 
Sunset FRS Plus 10-2010
  Sunset HRS Plus 04-2011
 
  Banner Advancement  
Banner Advancement  Kickoff 04-2006
Banner Advancement  – System configured 05-2007
Banner Advancement  Go-Live 07-2007
 
  Banner Student (includes Financial Aid)  
Banner Student & Financial Aid Kickoff 10-2006
Recruitment Plus Go-Live [Undergrad Prospect Mgmt] 09-2008
Hobson's Go-Live [Graduate Prospect Management] 09-2008
Banner Admissions  Go-Live 09-2008
Powerfaids Go-Live 02-2009
Banner Student Registration Go-Live 03-2009
 
  Banner Finance  
Banner Finance Chart of Accounts (COA) Training 01-2007
Banner Finance COA (First-Draft) completed 01-2009
Banner Finance COA Completed 07-2010
Banner Finance Kickoff 12-2008
            √ Banner Finance  Go-Live 07-2010
 
  Banner HR  
Banner Human Resources Kick-off 09-2009
            √ Banner Human Resources Go-Live 12-2010
     
 

Banner Other

 
            √ Banner Workflow Go-Live 02-2011
            √ Enterprise Document Management Kick-Off 01-2011
  Enterprise Document Management Go-Live  
 
  Infrastructure & Database  
Infrastructure: New Sun Hardware delivered 05-2006
Infrastructure: Sun Hardware Installation Completed 02-2007
Oracle Production configured 06-2007
Upgrade to Banner v8 03-2010
 
  University Portal - My.Fordham.edu  
University Portal Kickoff 06-2006
Portal Go-Live for Advancement 07-2007
Alumni Social Network Go-Live [Fordham Circle] 02-2008
My.Fordham.edu General Go-Live (for entire community) 11-2008
 
  Lessons Learned / Business Process Improvements  
Student Kick-Off 10-2010
Advancement Kick-Off 11-2010
  Finance Kick-Off 04-2011
  HR Kick-Off 04-2011
 
  Business Intelligence  
Business Intelligence Tool selected 12-2008
√  Operational Data Store 05-2009
  Data Warehouse 09-2011
 
  Project Close-out Completed 12-2011