Purchase Order Changes
A Change Order is a formal modification to an existing, approved Purchase Order. It is required whenever there is a significant material change to the original agreement before the invoice is paid.
When a Change Order is Required:
-
Price Increases: The actual cost exceeds the original PO amount by more than a standard variance (typically 10% or $100, whichever is greater).
-
Quantity Changes: Adding or removing items, or changing the scope of services requested.
-
Accounting Changes: Changing the budget index, fund, or account code being charged.
-
Cancellations: Partially or fully canceling remaining lines on an active PO.
The Process: Departments must submit a formal Change Order request through FINBUY (Jaggaer), detailing the exact modifications and providing justification.
-
Important: No work should be performed by the vendor, and no additional goods should be accepted, until the revised Change Order has been officially approved and issued by the Purchasing Department.